Mexico's 2026 sewer repairs

Funded or underway

Get monthly updates
Last updated Reviewed by Stacy WillisSummarized from public sources with the help of AIHow this site is made
United StatesMexicoTijuanaPacific OceanPump Station 1Tijuana sewer system
Where this project sits in the system.Open this on the map

What this project is

A bundle of collector and interceptor work in Tijuana funded under Mexico's 2026 commitment. As of late September 2026: the Insurgentes Collector, started June 29, 2026, had 205 of 5,431 meters built and is expected in July 2027. Rehabilitation of the Poniente Interceptor (460 of 705 meters), Oriente Interceptor (421 of 1,600 meters) and Carranza Collector (986 of 1,100 meters) is expected in December 2026. Mexico has committed funds for the PB-Matadero and Laureles PB-2 pump stations, with construction expected to start in December 2026.

Problems it would fix

Sources

  1. U.S. EPA, Tijuana River watershed public updates, quarterly updates to September 2026